The broadband rollout is again moving forward! I have spoken with the internet provider a couple times in the last 2 weeks, getting together the information needed to proceed. He will be working with the township in the next few weeks on the permitting process. it could take a few months to move everything through the township so we will have to be patient.

The provider’s biggest concern in having enough customers. He indicated he needs 45 customers to offer a high level of service and sustain the business. He mentioned he will probably send out a mailer with some details and will likely use that to gauge interest in his service. I suspect it will take him a few weeks to get that out as he has some work to do with the township first.

I’ll keep everyone posted when I hear more. Thanks for your patience and support!